PROJECT DATA:

  • Large scale sewer purification
  • Capacity: 35.00 Mℓ/d
  • Earthworks, concrete work, access roads, pipelines, screw pumps, aerators, fencing, building
  • Specialised piling operation underneath structures for earthworks

PROJECT OVERVIEW:

  • The Welgedacht Sewer Purification plant was a complicated project due to the stringent technical specifications.
  • The project was a joint venture between four contractors. The co-ordination between these parties was an achievement.
  • In spite of these challenges, the project came in under-budget and on schedule.
  • Engkon took away several learnings from this project – In particular, the need to be flexible to change to client needs; and the co-ordination and cooperation required for success.