6ML Reservoir & Distribution

 

$

1997

Start Date

$

1997

Completion Date

$

R7.8 million

Project Value

$

Rustenburg

Location

PROJECT DATA:

  • 400/275/88kV substation
  • GIS specialised building
  • Earthworks, buildings, roads, concrete, fencing, storm water drainage system
  • 40 000m3 for earthworks
  • 1700m3 concrete
  • 1500m fencing
  • 200+ foundation structures

PROJECT OVERVIEW:

  • Sebenza, the largest substation of City Power, was a complicated but successful build. The technology was new and there were also multiple stakeholders that had to be co-ordinated.
  • Engkon was one of the contractors to CONCO and had 5 sub-contractors of its own and managed 130 people.
  • Engkon took away several learnings from this project – In particular, the importance of choosing the right people; the extra lead times when dealing with multiple stakeholders; and the importance of strong relationships and collaboration.